Design 1

This is a simplified version of the original design. The design consists of a hand winch placed above the trunk and has a counterweight to allow steadyness within the crane.
The advantages and disadvantages of this design are stated below.
Advantages
Bearings will allow the crane to rotate , therefore there is greater accessibility for different angles.
The base is steady with four adjustable ( anglular adjustment ) legs.
The base does not take up much space and can access areas which are difficult.
Disadvantages
The bending moments and stress analysis will more complex .
The crane would suffer from the possibility of tipping over.
Bearings make the system more complex.

No comments:

Post a Comment

Project Schedule

  • Initial Group Meeting Tues 09.03.10 - 10.30am
  • Project Meeting [loft] 11.03.10 - 1pm
  • Project Meeting [loft] 16.03.10 - 10am
  • Project Meeting [loft] 18.03.10 - 10am
  • Project Meeting [loft] 22.03.10 - 10am
  • Project Meeting [loft] 25.03.10 - 1pm
  • Project Meeting [loft] 19.04.10 - 10am
  • Project Meeting [loft] 22.04.10 - 1pm
  • Tender Proposal Due - 23.04.10
  • Project Meeting [loft] 26.04.10 - 9.00am
  • Project Meeting [loft] 28.04.10 - 08.00am
  • Tender Presentation [mb 568] 28.04.10 - 10am
  • Group Blog Deadline - 28.04.10 - 23.59